Building the Future,
Step by Step
See how each milestone—from land acquisition to the projected opening—has brought us closer to launching a school that will serve hundreds of students each year. This timeline reflects our commitment to creating a safe, stable, and inspiring space where education opens the door to a brighter future.

July 2023
Land Acquisition
Securing land in Tororo was the very first step in making this dream real. With two acres officially dedicated to the school, we had the space, the vision, and a clear starting point for what would become a life-changing project.
2024
Design, Plans, Permits
Throughout the year, careful attention was given to the planning process. From architectural drawings to securing permits, every detail was thoughtfully designed to ensure the school would be safe, functional, and built to last.


April 2025
Groundbreaking
Breaking ground marked a powerful and emotional milestone. More than just moving soil, it was the beginning of something bigger—laying the path for education, opportunity, and brighter futures for hundreds of students.
May 2025
Foundation
The foundation was carefully poured with strength and purpose. More than just concrete, it represents the foundation for dreams, growth, and lasting impact—supporting everything that will rise above it.


June 2025
Framing and Exterior Walls
With framing and exterior walls in place, the school began to take visible shape. Every beam and brick brought the structure to life, making it easier to imagine the students who will walk these halls.
July 2025
Roof
Once the roof was added, the building became a place of shelter and safety. This critical step protected everything beneath it and moved us one step closer to opening day.


September 2025
(projected)
Windows and Doors
Windows and doors will be installed to give the school its sense of openness and connection. With natural light and airflow in place, each classroom will begin to feel complete, preparing to welcome its first students.
October 2025
(projected)
Core Installations
Core installations like plumbing, electrical, plastering, and painting will bring the building to life. These essential systems will make the structure functional and ready for the final stage of preparation.


November-December 2025
(projected)
Interior Completion
Interior finishes and furnishings will transform the building into a true learning space. From desks and chairs to welcoming touches, every element will be placed with care to support a thriving classroom environment.
January 2026
(projected)
Open For Enrollment
With the school completed and classrooms fully prepared, enrollment will begin in anticipation of the 2026 school year. This exciting step will mark the final preparations—turning readiness into reality and setting the stage for meaningful impact.


February
(projected)
Start of School Term
When the 2026 school term begins, a dream years in the making will come to life. For founder Sandra Abbo, it will be the fulfillment of a heartfelt mission to uplift, educate, and empower. Students will fill the halls with laughter, learning, and purpose—ushering in a new chapter of hope, opportunity, and lasting change for generations to come.